Light Rail announces barrier removals

Posted 9 July 2018

The construction of Light Rail is one step closer after the announcement that the barrier arrangements in all zones across the alignment will moved or reduced by November this year. 

This follows the substantial completion of civil construction across the CBD and Randwick. 

The barrier removal completion date are as follows: 

  • CBD North (zones 1-7) - By November 2018
  • CBD South (zones 8-12) - By January 2019
  • Surry Hills and Moore Park (zones 13-22) - By November 2018
  • Randwick (zones 23-27) - By February 2019
  • Kingsford / Kensington (zones 28-31) - By February 2019

Transport NSW suggest there will be less noise and intrusion and less space will be required as operations continue.

For more information about this work, please call 1800 684 490 or email SLRcommunity@acciona.com.

  • For urgent enquiries or complaints call the Light Rail 24-hour Construction Response Line: 1800 775 465
  • For the latest information on traffic conditions related to construction in the area, visit www.livetraffic.com
  • For further information about the CBD and South East Light Rail Project, go to www.sydneylightrail.transport.nsw.gov.au