Light rail work update for Randwick from 1 September to 1 December 2018

Posted 4 September 2018

The next three months will continue to see construction works take place as part of creating a modern, reliable and sustainable public transport system.

Out of hours work will continue from 1 September to 1 December 2018, weather and site condition permitting.

Due to high daytime traffic volumes and to ensure pedestrian safety, these works will be completed between 6pm to 6am Sunday to Thursday nights, and from 8am to 5pm Sundays.

Out of hours work will take place on a maximum of four nights per week in a particular location, unless otherwise notified.

In some circumstances that construction work has to be taken at night to minimise the traffic impact, and to ensure pedestrian safety.

  • Pedestrian diversions will be in place for work being undertaken on footpaths.
  • Road occupancy licences for work on live traffic lanes are usually only granted at night, to minimise traffic and access impacts.
  • Heavy load deliveries normally take place at night, when traffic volumes are lower.
  • For more information on the three month lookahead, click here. 

More Information

  • For more information about this work, please call 1800 684 490 or email SLRcommunity@acciona.com.
  • For urgent enquiries or complaints call the Light Rail 24-hour Construction Response Line: 1800 775 465
  • For the latest information on traffic conditions related to construction in the area, visit www.livetraffic.com
  • For further information about the CBD and South East Light Rail Project, go to www.sydneylightrail.transport.nsw.gov.au.